Leesville Cryogenic Processing Facility

Project Name:

Leesville Cryogenic Processing Facility

Project Description:

The Leesville Plant is a 200 MMSCFD cryogenic processing facility located in Leesville, Ohio. The peak manpower during the project was 91 employees and the project was completed with a total of 100,000 man-hours with zero OSHA recordable and zero lost time accidents. Installation of plant power consisted of two circuits of (6) parallel 3-Phase 750 MCM 15 KV Cable running through duct bank, transitioning to overhead for road crossing, and  back to duct bank. Duct bank consisted of 14,000’ of 6” conduit. Scope of work also included 280,000’ Instrument Cable, 127,000’ Power Cable, 1500 Loop Checks, and 26,000’ Heat Trace.

    8 Years & counting without a Lost Time Accident!