Liquids Recovery Facility

liquids_rocovery_facility.png.pngIn 2011, Ardent completed electrical and instrumentation construction for a gas plant near Watford City, North Dakota.

This gas plant is a 100MMSCFD liquid recovery unit. This nine month project included installation of 10,000 feet of cable tray, 64,000 feet of above ground conduit, 42,000 feet of underground conduit and 435,000 feet of cable, while peaking at 135 craft and staff.

All cable was pulled in an 11 week period. In addition to the primary electrical scope Ardent also installed and connected over 550 instruments, 27,000 feet of ground wire, 183 light fixtures, over 90 panels, transformers and junction boxes and 12,000 feet of electrical heat trace. Ardent completed this work with zero recordable injuries.